Cambridge, Ontario · 2011–2012

401 Eastbound Service Centre

ClientSuncor Energy Products Partnership
ScopeDecommission / Demolish / Remediate

The scope of work pertained to the decommissioning, demolition, and remediation of a service station and adjacent buildings.

Clarkway Construction utilized its ALLU Bucket (crusher/screener) to reduce demolition debris, screen debris from the soil, and crush frozen material suitable for backfill. During remediation procedures, the crusher/screener allowed frozen clean native material, otherwise suitable for backfill, to be crushed and screened for optimal compaction.

Contaminated groundwater was found during drilling activities; Clarkway Construction activated the certificate of approval for our water treatment system to treat and discharge the impacted water to an adjacent surface watercourse.

1.4M L
Groundwater treated & discharged
ALLU
Crusher / screener deployed
2011–12
Project timeframe
Trenton, Ontario · 2009

401 Eastbound Service Centre

ClientPetro Canada (Suncor Energy Products Partnership)
ScopeDecommission / Demolish / In-situ Remediation

The service centre and adjacent restaurants were decommissioned and demolished. An estimated 6,000 metric tonnes of soil was anticipated to be contaminated with hydrocarbons; well reports determined groundwater was contaminated with SVOCs, VOCs, BTEX, and hydrocarbons. Clarkway Construction performed all work in conjunction with the environmental consultant retained by the client.

Clarkway Construction utilized ORC (Oxygen Release Compound) as a method of in-situ remediation. An estimated half of the contaminated soil originally arranged for off-site disposal was made suitable for backfilling purposes instead.

Clarkway Construction activated the Certificate of Approval for our water treatment system. Impacted groundwater was treated and dispersed to an adjacent surface watercourse.

2.2M L
Groundwater treated & discharged
6,000 T
Soil managed (est.)
ORC
In-situ remediation method

A project on the horizon?

Two decades of Suncor / Petro Canada service-centre work, from decommissioning to full remediation.